Photo Credits: Irish Independent

Children’s Hospital completion timeline remains unclear

Author: Bianca Odron
Share

The National Paediatric Hospital Development Board (NPHDB) has confirmed that no revised completion date has yet been agreed for Ireland’s National Children’s Hospital following the latest missed delivery milestone, extending uncertainty around one of the State’s most significant public infrastructure programmes.

According to correspondence submitted to the Public Accounts Committee (PAC), project contractor BAM provided an updated programme of works and associated documentation after missing the most recent substantial completion deadline of 30 April. The board reviewed the submission and subsequently requested additional information in May, with assessment of the revised programme remaining ongoing.

While negotiations continue around the updated schedule, the board indicated that its immediate priority is identifying opportunities to gain phased access to completed areas of the hospital before full project completion. Early access to critical operational spaces, including critical care units and operating theatres, is intended to support commissioning activity and reduce the overall time required before services can become operational.

The latest developments highlight the continued importance of procurement governance, contract administration and programme controls in large-scale public projects. Beyond physical construction, project delivery requires ongoing management of timelines, design coordination, contractual obligations and stakeholder oversight to support delivery outcomes.

Information provided to the PAC also demonstrated the scale of change management activity across the programme. Since 2019, approximately 50,000 revised drawings and project documents have been issued collectively by BAM and the NPHDB. Over the past 18 months alone, thousands of additional revisions have continued to move through project processes.

The board further reported that legal and professional expenditure associated with the programme includes €2.9 million for contract legal services and approximately €1 million for procurement advice, reflecting the scale and contractual complexity of the development.

The project continues to demonstrate the challenges of delivering major public infrastructure where programme management, procurement governance and delivery oversight remain closely linked. 

Explore the latest project update and oversight details at the original source.



Discover What's Happening

The National Procurement Awards 2026

October 22nd, 2026

Crowne Plaza Hotel, Santry

Stay Ahead in Procurement Excellence

Explore our newsletters

Join our Newsletter to receive the latest industry trends, expert tips, and exclusive insights delivered straight to your inbox!